Permits, trades and the order of work
Your designer flags which parts of the plan need a permit or a licensed trade. Moving a sink or adding a circuit for an island are the usual cases. Those are scheduled before the installers arrive, so the job runs in sequence. Demolition, rough plumbing and electrical, drywall, cabinets, countertop template, countertop install, backsplash, then finish plumbing and electrical.
Cabinets are installed first. The countertop is templated after they are set, never from the old layout, which keeps seams off the sink and the overhang even. Most kitchen remodels take 4 to 8 weeks from start to finish, depending on scope.